Avenida – Rio Salado/Broadway Rd

Category
Wet Utilities
About This Project

Owner: City of Phoenix

Construction Dates: Jun 2014 – Jun 2016

 

As a subcontractor to Kiewit Infrastructure West, Auza Contracting performed 19 waterline vertical realignments (6” – 24”), 42 fire hydrant relocations, 86 water service and backflow preventer relocations, 52 water valve relocations, 2 fire department connection relocations, and relocated over 400’ of sanitary sewer lines to allow for the expanded Right of Way and improvements on Broadway Road.