Wickenburg Airport Mid-Field Apron Construction

Category
Manhole and Sewer, Shotcrete, Wet Utilities
About This Project

Owner: Town of Wickenburg

Construction Dates: Aug 2015 – Nov 2015

 

As a subcontractor to Grey Mountain Construction, Auza Contracting installed over 2,200’ of 8” waterlines, 1,800’ of 8” and 2” sewer lines, 750’ of 42” and 24” storm drain pipe, as well as numerous 3 relief valves, 4 fire hydrants, 9 water valves, and 3 sewer manholes. Auza Contracting also installed over 1,000 SY of shotcrete to complete a drainage channel as part of the project.